The Bar Council of India does not permit advertisement or solicitation by advocates in any form or manner. By accessing this website, www.khaitanco.com, you acknowledge and confirm that you are seeking information relating to Khaitan & Co of your own accord and that there has been no form of solicitation, advertisement or inducement by Khaitan & Co or its members. The content of this website is for informational purposes only and should not be interpreted as soliciting or advertisement. No material/information provided on this website should be construed as legal advice. Khaitan & Co shall not be liable for consequences of any action taken by relying on the material/information provided on this website. The contents of this website are the intellectual property of Khaitan & Co.

Please accept the above
Close

Search

See all results for ""

CERC confirms gradual rollback of ISTC waiver for RE projects based on wind / solar or combination of both

17-Jul-2025

Introduction

The Central Electricity Regulatory Commission (CERC), vide Notification dated 26 June 2025, has notified the CERC (Sharing of Inter-State Transmission Charges and Losses) (Fourth Amendment) Regulations, 2025 (Fourth Amendment Regulations).

Aligned with the policy priorities of the Ministry of Power, Government of India, the Fourth Amendment Regulations seek to support the expansion and integration of Renewable Energy (RE) sources, Battery Energy Storage Systems (BESS), and green hydrogen / ammonia plants into the national grid framework.

Notably, the CERC has confirmed the industry-wide speculation of gradual phasing out of the waiver for Inter-State Transmission Charges (ISTC) on RE Generating Systems based on wind or solar source (REGS) and Renewable Hybrid Generating Systems based on a combination of wind and solar source (RHGS), based on the commissioning of such generating systems.

While changes have also been affected for BESS and hydro generating stations / Pumped Storage Projects (PSP) and waiver of their ISTC, the Fourth Amendment Regulations have for the first time introduced a timeline for waiver of ISTC for REGS based on offshore wind and green ammonia/hydrogen plants.

A 100% waiver of ISTC charges has been granted, for 25 years for (i) the REGS based on offshore wind commissioned by 31 December 2032; and (ii) green hydrogen/ammonia plants as a drawee designated ISTC customer (DIC), commissioned up to 31 December 2030. Interestingly, as a drawee DIC, green hydrogen / ammonia plants sourcing at least 51% power from REGS, RHGS or hydro generating stations, are entitled to the highest eligible category of waiver i.e., waiver granted to such plants vis-à-vis the waiver granted to the source they are connected to.

It is understood that various industry stakeholders had sought an extension of the existing waiver regime for REGS, RHGS, hydro generating stations / PSP and BESS, expressing concerns that the withdrawal of such waivers may adversely impact project viability and potentially lead to higher tariffs for end consumers.

Key changes for REGS, RHGS and BESS

The timelines governing ISTC waiver eligibility for REGS and RHGS remain unchanged under the Fourth Amendment Regulations. Specifically, a 100% waiver continues to apply to such projects commissioned by 30 June 2025, with a gradual reduction in the waiver percentage for projects commissioned thereafter.

In respect of BESS, the regulatory treatment has now been bifurcated into 2 distinct categories:

  1. BESS co-located with REGS and charged exclusively from such REGS at the same substation; and
  2. All other BESS configurations, including those connected at substations without REGS, or those charged from the grid or other sources.

For the latter category, the waiver timeline remains consistent with the pre-amendment framework. However, the Fourth Amendment Regulations introduce a significant concession for the first category i.e., BESS units charged exclusively from co-located REGS and commissioned by 30 June 2028 are now eligible for a 100% ISTC waiver for a period of 12 years.

Importantly, REGS, RHGS and BESS may still qualify for a full waiver of ISTC, even if they are not commissioned by the cut-off date of 30 June 2025, subject to the fulfilment of the following key conditions:

  1. The project must have had a Scheduled Commercial Operation Date (SCOD) on or before 30 June 2025.
  2. The project must have achieved commissioning within the extended period granted for SCOD.
  3. Such extension must have been granted due to:
  1. a force majeure event (including non-availability of the transmission system); or
  2.  reasons not attributable to the project developer.
  1. If the SCOD is extended beyond 30 June 2025, each extension must not exceed 6 months at a time.
  2. A maximum of 2 such extensions is permitted.

Conclusion

The Fourth Amendment Regulations, and the framework for ISTC waiver therein, come at a pivotal moment, as India accelerates efforts to achieve its ambitious target of 500 GW of non-fossil fuel-based capacity by 2030, in alignment with its Nationally Determined Contributions under the Paris Agreement.

While the CERC has not provided any specific rationale for declining to extend the ISTC waiver timelines for REGS and RHGS-based projects, the Fourth Amendment Regulations do offer a limited safeguard for developers unable to achieve commissioning by 30 June 2025, where delays are attributable to force majeure events or other factors beyond the developer’s control.

It remains to be seen whether the Central Government or other relevant authorities will introduce additional policy or regulatory measures to sustain the momentum in wind, solar, and hybrid energy deployment, a momentum that the ISTC waiver regime has significantly helped foster over the past several years.

  • Divya Chaturvedi (Partner); Srishti Rai (Principal Associate) and Rikit Shahi (Associate)

For any queries please contact: editors@khaitanco.com

Divya Chaturvedi (partners)

We have updated our Privacy Policy, which provides details of how we process your personal data and apply security measures. We will continue to communicate with you based on the information available with us. You may choose to unsubscribe from our communications at any time by clicking here.

For private circulation only

The contents of this email are for informational purposes only and for the reader’s personal non-commercial use. The views expressed are not the professional views of Khaitan & Co and do not constitute legal advice. The contents are intended, but not guaranteed, to be correct, complete, or up to date. Khaitan & Co disclaims all liability to any person for any loss or damage caused by errors or omissions, whether arising from negligence, accident or any other cause.

© 2024 Khaitan & Co. All rights reserved.

Mumbai

One World Centre
10th, 13th & 14th Floor, Tower 1C
841 Senapati Bapat Marg
Mumbai 400 013, India

Mumbai

One Forbes
3rd & 4th Floors, No. 1
Dr. V. B. Gandhi Marg
Fort, Mumbai 400 001

Delhi NCR (New Delhi)

Ashoka Estate
11th Floor, 1105 & 1106,
24 Barakhamba Road,
New Delhi 110 001, India

Kolkata

Emerald House
1B Old Post Office Street
Kolkata 700 001, India

Bengaluru

Embassy Quest
3rd Floor
45/1 Magrath Road
Bengaluru 560 025, India

Delhi NCR (Noida)

Max Towers,
7th & 8th Floors,
Sector 16B, Noida
Uttar Pradesh 201 301, India

Chennai

8th Floor,
Briley One No.30
Ethiraj Salai
Egmore
Chennai 600 008, India

Singapore

Singapore Land Tower
50 Raffles Place, #34-02A
Singapore 048623

Pune

Raheja Woods
03-108-111, 3 Floor
8, Central Avenue, Kalyani Nagar
Pune - 411 006, India

Gurugram (Satellite Office)

Suite No. 660
Level 6, Wing B,
Two Horizon Center
Golf Course Road, DLF 5
Sector 43, Gurugram
Haryana 122 002, India

Ahmedabad

1506 - 1508, B-Blockr
Navratna Corporate Parkr
Iscon Ambli Road, Ahmedabadr
Gujarat - 380058