The Bar Council of India does not permit advertisement or solicitation by advocates in any form or manner. By accessing this website, www.khaitanco.com, you acknowledge and confirm that you are seeking information relating to Khaitan & Co of your own accord and that there has been no form of solicitation, advertisement or inducement by Khaitan & Co or its members. The content of this website is for informational purposes only and should not be interpreted as soliciting or advertisement. No material/information provided on this website should be construed as legal advice. Khaitan & Co shall not be liable for consequences of any action taken by relying on the material/information provided on this website. The contents of this website are the intellectual property of Khaitan & Co.

Please accept the above
Close

Search

See all results for ""

Domestic Arbitral Award Challenge: Proof to be furnished by Affidavit, Trial only in the rarest cases

05-Sep-2018

On the anvil of the proposed amendment in the Arbitration and Conciliation Act, 1996 (Act), on 20 August 2018, the Supreme Court of India in Emkay Global Financial Services Ltd. v. Girdhar Sondhi (Emkay case) has clarified that ordinarily, at the stage of challenge of arbitral award, only the arbitral tribunal’s record is to be considered to determine the grounds of challenge. If matters beyond such record are at issue, parties should ‘furnish proof’ of the grounds of challenge only by affidavits. Cross-examination of those testifying cannot be allowed unless ‘absolutely necessary’.

The Arbitration and Conciliation (Amendment) Bill of 2018 (Bill), based on the recommendations of Justice B.N. Srikrishna Committee, seeks to do away with the requirement of ‘furnishing proof’ at the stage of challenge to an arbitral award altogether. The Bill provides that the challenge to an arbitral award be considered only on the basis of arbitral tribunal’s record.

Background

Emkay case arose out of a dispute between Emkay Global Financial Services Ltd, a registered broker with the National Stock Exchange (Emkay Global) and its client, Girdhar Sondhi. Mr Sondhi initiated arbitration proceedings against Emkay Global for recovering his losses. The venue of the arbitration was at New Delhi. Mr Sondhi’s claim was rejected by the arbitral tribunal.

Mr Sondhi challenged the award under Section 34 of the Act before the New Delhi District Court which set aside the challenge on the ground of lack of territorial jurisdiction. However, on appeal, the Delhi High Court held that there is a dispute between the parties regarding territorial jurisdiction, presumably outside the arbitral tribunal’s record. Accordingly, the High Court required that District Court to ‘frame an issue and permit the parties to lead evidence on the same’.

Emkay Global successfully sought special leave from the Supreme Court to appeal.  The Supreme Court decided that there is no dispute as to territorial jurisdiction and, by agreement of the parties, the Courts at Mumbai alone would have jurisdiction to entertain the challenge to the arbitral award. However, the Supreme Court also took up the issue of whether mini trial is at all permissible at the stage of proceedings under Section 34 of the Act (Section 34 stage).

Supreme Court does away with mini-trial at Section 34 stage

In the Emkay case, the Supreme Court considered its precedent in Fiza Developers & Inter-Trade Pvt. Ltd. v. AMCI (India) Pvt. Ltd, (2009) 17 SCC 796, various judgments of the Delhi Hight Court and the recommendations of Justice B.N. Srikrishna Committee and the effect of additions of Section 34(5), 34(6) in the Act which prescribe a one year time line to decide a challenge to arbitral awards.

Justice R.F. Nariman opined that the law laid down in in Fiza Developers & Inter-Trade Pvt. Ltd. v. AMCI (India) Pvt. Ltd, (2009) 17 SCC 796 that no issue can be framed at Section 34 stage (being a summary procedure) is good law. In view of the amendments to the Act, i.e. Sections 34(5) and 34(6), requiring speedy disposal of Section 34 challenges, the Supreme Court has declared that ordinarily, nothing beyond the arbitral tribunal’s record needs to be looked at, during the Section 34 stage. In rare cases however, when matters are beyond the record of the arbitral tribunal, parties should bring the issues to the Court’s notice by way of affidavits. Cross-examination at the Section 34 stage should not be allowed unless absolutely necessary.

Comment

The Emkay case has brought clarity and has virtually obviated a mini trial at the Section 34 stage. This would go a long way in reducing the time taken in deciding challenges to domestic arbitral awards. The case leaves open to the Courts to allow parties to file affidavits in appropriate cases where the grounds cannot be proved from the arbitral tribunal’s record and, if absolutely necessary, cross-examine those who file affidavits.

-  Susmit Pushkar (Partner), Anchit Oswal (Principal Associate) and Gaurav Sharma (Associate)

For any queries please contact: editors@khaitanco.com

Susmit Pushkar (partners)

We have updated our Privacy Policy, which provides details of how we process your personal data and apply security measures. We will continue to communicate with you based on the information available with us. You may choose to unsubscribe from our communications at any time by clicking here.

For private circulation only

The contents of this email are for informational purposes only and for the reader’s personal non-commercial use. The views expressed are not the professional views of Khaitan & Co and do not constitute legal advice. The contents are intended, but not guaranteed, to be correct, complete, or up to date. Khaitan & Co disclaims all liability to any person for any loss or damage caused by errors or omissions, whether arising from negligence, accident or any other cause.

© 2021 Khaitan & Co. All rights reserved.

Mumbai

One Forbes
3rd & 4th Floors, No. 1
Dr. V. B. Gandhi Marg
Fort, Mumbai 400 001

Chennai

119/65, First Floor
Dr Radhakrishnan Salai
Mylapore
Chennai 600 004,
India

Noida

Max Towers
7th & 8th Floors
Sector 16B, Noida
Gautam Buddh Nagar
201 301 India

Singapore

Ocean Financial Centre
#37-02 10 Collyer
37th Floor Quay
Raffles Place 049315,
Singapore